Sa vethuen Doc #: PCO 22
dc Methuen Ref. Document:
PROJECT NAME: Date: 18-Jun-20
Nashua Energy Recovery
PROJECT NO; 181012
PHASE
COST SUMMARY SHEET
Piping Relocation for Generator Fngines
A NMC Labor (Recap Sheet}: $825.62
B McC Materials, & Equipment (Recap Sheet): $136.00
C MC Fae (A x 15%) + (B x 15%): $144.24
D Subtotal MC Work (A+B+C); | $ 4,105.87
E Total Subcontractors (Below): $640.00
F MG Mark-up on Subcontractor Work (5%, 7.5% or 10%): | $ 55.65
G Bond (1%) and General Liability (1%): $36.03
Total Proposal (D+E+F+G); $ 4,837.55