Mrz. William Keating
COR review
G60
The table below summarizes the total value of the work, which will be assed value of the work
perfonned and taken at % value.
The claimed cost of work (take the lower of the higher estimate or the claim)
Claimed Cost | Fair Market Value | Allowable Mark-up** | Work Value Assessment
of Work of Work scope
$1,837 $1,350 (includes 15% on MC Work $1,782
materials & 10% on Subs (<$50k)
equipment)* 7-1/2% on Subs ($50-
100k)
5% on Subs (>100k)
*Market Value Assessment-$1,188 to $1,782 (+/- 20%)
Work Value | Deduct Assessment | Mark down by 50% Total Direct Value
Assessment as noted above Assessment
31,782 ($0) 5891 $891
Detailed Review-Schedule
Methuen made a claim for schedule adjustment but has not provided a CPM (critical path
method) schedule showing how this item moved onto the critical path. Their schedule claim is
therefore evaluated at 0 days. Therefore we recommend 0 days be awarded.
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 1 0 0
Conclusion
Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question.
Waldron recommends approving $891 of the claim as noted above @ days of schedule relief.
If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com
Sincerely
Waldron Engineering & Construction, Inc.
Jeremy P. Siudth, PE.
Jeremy Smith, P.E.