B-6.1
CHANGE ORDER
No. 007
PROJECT: Energy Recovery Upgrade DATE OF ISSUANCE: 7/15/20
OWNER: City of Nashua, NH
229 Main St, Nashua, NH
(Address)
CONTRACTOR: Methuen Construction Co., Inc OWNER’s Project No. [FB0501-091618
CONTRACT FOR: Energy Recovery Uparade ENGINEER Waldron Engineering & Construction, Inc.
at Nashua NH Wastewater Treatment ENGINEER’s Project No. 359.01
You are directed to make the following changes in the Contract Documents.
Description:
Purpose of Change Order:
Justification:
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
$ 1,787,378.00
Original Contract Time
280 (final completion)
(days or date}
Previous Change Orders Net change from previous Change Orders
$ 124,210.27 10
(days)
Contract Price prior to this Change Order
3 1,911,588,.27
Contract Time prior to this Change Order
290 (final completion)
(days or date)
Net Increase (Decrease) of this Change Order
$ 39,315.00
Net Increase (decrease) this Change Order
0
(days)
Contract Price with all approved Change Orders
$ 1,950,903.27
Contract Time with all Change Orders
290 (final completion)
(days or date}
This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.
Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that
the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.
RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: ainet#, BY: By: By:
ineer Owner Contractor NHDES
7/15/20
Bate Date Bate Date