WALDRON
July 7, 2020
Mr. William Keating
Project Engineer
Nashua Waste Water Treatment Facility
Via Email
Reference: Contract Amendment-2
Construction Administration-Extension of Resident Engineering Services
Dear Mr. Keating,
Thank you for the opportunity to present NWWTF with this proposal to perform additional
engineering and design services for the Construction Administration-Resident Engineering portion
of the work, related to the extension of the project site construction period.
Summary
Waldron Engineering proposes to add resident engineering services related to supporting the project
site through the extended on-site construction period.
Waldron notes that the general contractor’s on -site construction has been extended by seven (7)
months, which is due in part to the COVID-19 crisis.
Waldron notes that the original contract has sixteen (16) days of on-site visits, and that the extended
construction period has required additional visits not envisioned by the original contract, which will
now number Thirty-one (31) which has entailed fifteen (15) additional visits.
Project Implementation plan
Project plan will be implemented upon release by client. Project implementation is as follows:
Support continuing contractor RFT’s
Support contractor continuing submittal reviews
Continue periodic inspections of the project sight
Review and provide opinions on contractor potential change orders
e Review with Owner noted concerns from site visits
Deliverables
Waldron will implement the work plan above and deliver reports to the Owner
e = Site visit reports
Completed RFI response
e Completed submittal reviews
e Completed Change order Reviews
Clarifications
Waldron did not perform periodic site visits at the height of the COVID-19 crisis, when no active
work was being performed, and has not included that time here within.
37 INDUSTRIAL DRIVE... SUITE G-1 -. EXETER, NH.03833 (603) 772-7153