Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$171,759.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: August 7, 2620
Ready for final payment: August 21, 2020
Net changes from previous Change Orders
$0
Net change from previous Change Orders
0 days
Contract Price prior to this Change Order
$171,759.00
Contract Times prior to this Change Order
Substantial completion: August 7, 2020
Ready for final payment: August 21, 2020
Net Increase (decrease) of this Change Order
$40,000.00
Net Increase (deerease) of this Change Order
21 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial completion: August 28, 2020
$211,759.00
Ready for final payment:September 11, 2020
REC D: ACCEPTED: APPROVED:
By: By: By:
niell Hutison Contractor Mayor Jim Donchess
City Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: 07/27/2020 Date: Date:
Change Order # 1 2 of 2 2020 Sidewalk Program