  2. Finance Committee - Agenda - 8/5/2020 - P39

Finance Committee - Agenda - 8/5/2020 - P39

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
39
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

CHANGE ORDER

No. 1
PROJECT: 2020 Sidewalk Program
OWNER’S CONTRACT NO: IFB0851-032720
EXECUTED CONTRACT DATE: 6/11/2020
DATE OF ISSUANCE: Ti24/2020 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 156959
CONTRACTOR: RWC Enterprises
ENGINEER: DPW Engineering

You are directed to make the following changes in the Contract Documents:

1. The City will add to the Contract quantities for additional ADA improvements:
« Harbor Ave at East Hollis Street (McDonalds) east intersection corner,
« East Hollis Street at Spruce Street east intersection corner, (Wendy’s)
« East Hollis Street at Spruce Street west intersection corner (Nashua House of Pizza)

2. The City will add to the Contract the following items based upon unforeseen site conditions:
Item 604.4 Reconstructing/Adjusting Catch Basins and Inlets

Item 608.36 6” Reinforced Concrete Sidewalk

Item 609.56 Reset Granite Curb 6” High Back Curb

Item 646.51 Turf Establishment with Mulch, Loam, and Tackfiers

Unit costs provided for this work has been determined to be fair and reasonable.
Justification:

1. The project limits are adjacent to ADA deficient street corners on East Hollis Street at Harbor
Ave and at Spruce Street that should be upgraded to be ADA compliant prior to paving East
Hoilis Street.

2. The inclusion of the additional pay items will allow for:
a. Work to continue despite unforeseen field conditions.
b. Inclusion of restoration items for disturbance at the back edge of sidewalk.
c. Inclusion of heavy duty sidewalk construction in an area prone to truck turn damage.

Total compensation for the work described and for changes to the Contract Documents shall not
exceed $40,000.00.

Change Order # 1 / 1 of 2 2020 Sidewalk Program