City of Nashua, Public Works Division
Board of Public Works Meeting Date: July 23, 2020
Daniel Hudson, P.E., City Engineer
Engineering Department
2020 Sidewalk Program
Change Order No. 1
To approve Change Order No. 1 to the 2020 Sidewalk Program Contract with RWC
Enterprises of Nashua, NH for an amount not to exceed $40,000 funded through the
Southeast Quadrant Funds ($31,000) and Capital ($9,000). Funding will be through
Department: 160 Admin/Engineering; Funds: Trust and Capital; Account Category:
54 Property Services and Activity: Sidewalks.
In May a 2020 Sidewalk Program contract was approved to reconstruct
approximately 900 feet of sidewalk on the south side of East Hollis Street between
CVS and Harbor Avenue. Work includes construction of concrete pedestrian
sidewalk, resetting of curb, and ADA compliance improvements at Medical Center
Drive.
The purpose of this Change Order No. 1 is to address additional identified issues,
including constructing ADA compliant ramps and landings at three adjacent street
corners at the East Hollis Street/Harbor Ave/Spruce Street intersection, increasing
thickness of sidewalk at the East Hollis Street/Medical Center Drive intersection to
protect against damage from trucks, and improving matches to abutting properties
through widened sidewalk and back curbing.
A Change Order is still being negotiated. The not to exceed estimate is based on an
engineer’s estimate of probable cost for extended and new contract items.