Finance Committee - Minutes - 8/19/2020 - P25

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Wed, 08/19/2020 - 00:00
Meeting Description
Finance Committee
Document Type
Minutes
Meeting Date
Wed, 08/19/2020 - 00:00
Page Number
25
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_m__081920…

Belfort Valmont Sabre Green Mountain
Cost Monopole Tower $21,920 $31,100 $30,472 $23,719
Proposal Lighting Excluded Included $9,422 $8,790
Cable Ice Bridge Included Included Included $5,555
Structural Analysis Included Included Included $1,300
Foundation Plan Included Included Included $1,040
Total $21,920 $31,100 $39,894 $40,404
Estimated Freight Included $4,326 $6,213 $8,000
Total Including Estimated Freight $21,920 $35,426 $46,107 $48,404
Lead Time on Foundation Plan 4 Weeks 2 Weeks 3-5 Days 4 Days
Lead Time on Anchor Bolt Receipt 3 to 4 Weeks | 4 Weeks | 3-4 Weeks 3 Weeks
Lead Time on Tower Delivery 14 - 18 Weeks | 10 Weeks | 8-10 Weeks 7 Weeks
Optional Tower Unload, No Bid NoBid | $26,588 $35,850
ErectionInstall Lighting/Ice Bridge
T E ti kfill and
ower Excavation/backfill an No Bid NoBid | No Bid $39,000
Foundation
Proposal Evaluation
Qualifications and Experience 0% 28% 28% 30%
Overall Impression of Proposal 0% 8% 8% 10%
Cost Proposal 60% 55% 50% 45%
Overall Score 60% 91% 86% 85%

Page Image
Finance Committee - Minutes - 8/19/2020 - P25