To:
From:
Re:
B. Motion:
Attachments:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 27, 2020
Nick Caggiano, Superintendent
Parks and Recreation Department
Purchase and installation of a playground for Lincoln Park.
To approve the purchase and installation of a playground for Lincoln Park from
Ultiplay Playgrounds, Inc. of Uxbridge, MA pursuant to the Massachusetts state
contract # ¥C000510633FAC 104 in the amount of $97,421, Funding will be
through Department: 177 Parks and Recreation; Fund: Capital; Activity: Lincoln
Park Improvements.
Quote and concept drawing
The scope of work for this project includes the installation of a play structure and
poured in place playground surfacing. The Lincoln Park playground was removed
last year due to safety concems. Several types of playgrounds were looked at and
this modei will bring an element of nature to this urban setting. The goal is to
have the area prepped as part of the park renovations this fall and have the
playground installed late this fall or first thing in the spring depending on the
construction schedule and the weather. Uliiplay was the vendor that provided and
installed the Salem Street Tot Lot and the playground hand sanitizer stations this
year. Their work was very good and performed in a timely fashion.