22, FINAL ACCEPTANCE Upon completion of ali work under the contract, Independent Contractor
23.
24.
26,
shall notify the City of Nashua in writing of the date of the completion of the work and request
confirmation of the completion from the City of Nashua. Upon receipt of the notice, the City of
Nashua shall confirm to Independent Contractor in writing that the whole of the work was
completed on the date indicated in the notice or provide Independent Contractor with a written
list of work not completed. With respect to work listed by the City of Nashua as incomplete,
Independent Contractor shall promptly complete the work and the final acceptance procedure
shall be repeated. The date of final acceptance of a project by the City of Nashua shall be the date
upon which the Board of Public Works or other designated official accepts and approves the
notice of completion.
TAXES Independent Contractor shall pay all taxes, levies, duties, and assessments of every
nature due m connection with any work performed under the contract and make any and all
payroll deductions required by law. The contract sum and agreed variations to it shall include all
taxes imposed by law. Independent Contractor hereby indemnifies and holds harmless the City of
Nashua from any liability on account of any and all such taxes, levies, duties, assessments, and
deductions.
NON-WAIVER OF TERMS AND CONDITIONS None of the terms and conditions of this contract
shall be considered waived by the City of Nashua. There shall be no waiver of any past or future
default, breach, or modification of any of the terms and conditions of the contract unless
expressly stipulated to by the City of Nashua in a written waiver.
. RIGHTS AND REMEDIES The duties and obligations imposed by the contract and the nghts and
remedies available under the contract shall be in addition to and not a limitation of any duties,
obligations, rights, and remedies otherwise imposed or available by law.
PROHIBITED ENTERESTS Independent Contractor shall not allow any officer or employee of the
City of Nashua to have any indirect or direct interest in this contract or the proceeds of this
contract. Independent Contractor warrants that no officer or employee of the City of Nashua has
any direct or indirect interest, whether contractual, noncontractual, financial or otherwise, in this
contract or m the business of Independent Contractor. [f any such interest comes to the attention
of Independent Contractor at any time, a full and complete disclosure of the interest shall be
immediately made in writing to the City of Nashua. Independent Contractor also warrants that it
presently has no interest and that it will not acquire any interest, direct or indirect, which would
conflict in any manner or degree with the performance of services required to be performed under
this contract. Independent Contractor further warrants that no person having such an interest shall
be employed in the performance of this contract. If City of Nashua determines that a conflict
exists and was not disclosed to the City of Nashua, it may terminate the contract at will or for
cause in accordance with paragraph 8.
In the event Independent Contractor (or any of its officers, parmers, principals, or employees
acting with its authority) is convicted of a crime involving a public official arising out or in
connection with the procurement of work to be done or payments to be made under this contract,
City of Nashua may terminate the contract at will or for cause in accordance with paragraph 8.
Upon termination, Independent Contractor shall refund to the City of Nashua any profits realized
under this contract, and Independent Contractor shall be liable to the City of Nashua for any costs
incurred by the City of Nashua in completing the work described in this contract. At the
discretion of the City of Nashua, these sanctions shall also be applicable to any such conviction
obtained after the expiration or completion of the contract.
GC 10 of 11