Installation Schedule
Nashua Riverwalk Grid Board Timeline
Oct 16, 2020 - Jun 25, 2021 —
Name ~“ Start ~“ Finish Durati...
1 © Contract Signed 10/16/202C 10/16/2020 1 day
2 ©) _ Project Kickoff 1/4/2021 1/4/2021 1 day
3 © _ Confirm Bill of Materials for Fixture Orders 1/5/2021 1/22/2021 14 days
4 © Site Work - Kickoff & Mobilization 3/15/2021 3/15/2021 1 day
5 ©) Order Materials & Lead Time 2/1/2021 5/3/2021 66 days
6 O Installation of Conduit on Cotton Transfer Bridge 4/5/2021 4/9/2021 5 days
7 oO Installation of Lighting on Cotton Transfer Bridge and Demolition of existing lighting 4/12/2021 4/23/2021 10 days
8 ©) Installation of Conduit and Pole Bases West of EX-1 4/12/2021 4/23/2021 10 days
9 (©) Installation of Conduit and Pole Bases East of EX-1 4/26/2021 5/7/2021 10 days
io 6 Installation of Poles and Lights West of EX-1 and Demolition of Existing Lighting 4/26/2021 5/14/2021 15 days
11. ©) _ Installation of Poles and Lights East of EX-1 and Demolition of Existing Lighting 5/10/2021 5/28/2021 15 days
2- O System Start-up and Testing $/31/2021 6/1/2021 2 days
133. © © Punchlist 6/2/2021 6/18/2021 13 days
4 OO Project Closeout 6/21/2021 6/25/2021 5 days
Pricing
Item / Scope Price
Cotton Transfer Bridge $105,439
Riverfront Walkway $502,342
Main Street Bridge Not in Scope