Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 12/2/2020 - P72

Finance Committee - Agenda - 12/2/2020 - P72

By dnadmin on Mon, 11/07/2022 - 13:24
Document Date
Wed, 11/25/2020 - 15:47
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/02/2020 - 00:00
Page Number
72
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__120220…

To:

From:

Re:

B. Motion:

Attachment:

Discussion:

City of Nashua, Public Works Division

Board of Public Works Meeting Date: November 19, 2020

Daniel Hudson, P.E., City Engineer
Engineering Department

20619 CIPP Lining Project
Change Order No, 3

To approve Change Order No. 3 for the 2019 CIPP Lining Project with Kenyon
Pipeline Inspection of Queensbury, NY for the amount not to exceed $300,000.
Funding will be through Department: 169 Wastewater; Fund: Bond; Activity: Sewer
Rehab.

2019 CIPP Lining Project Change Order No, 3

Kenyon Pipeline Inspection was the low bidder of the 2019 CIPP Lining Project and has
performed well over the course of the contract. Change Order No. 1 was approved in
September 2019 without any cost changes and Change Order No. 2 was approved in
April 2020 for $1,500,000, The Engineering Department would like to continue to use
the services of Kenyon into early 2021 and seeks a $300,000 change order to continue
to video inspect sewer pipes during the winter to identify pipes that need replacement in
the 2021 construction season. Deteriorated sewers may also be lined under this change
order, as needed,

It is anticipated that a new pipe inspection and lining contract will be advertised in the
spring of 2021.

With this change order, the total contract value is $4,625,135.00.

Page Image
Finance Committee - Agenda - 12/2/2020 - P72

Footer menu

  • Contact