City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 20, 2018
David L. Boucher, Superintendent
Wastewater Department
Replacement Heating Units in Control Room and Cafeteria
To approve the purchase and installation of two new heating units in the Wastewater
Facility Control Room and Cafeteria for the amount of $15,574 from Armand E. Lemire
Co., inc. of Hooksett, NH. Funding will be through: Department: 169 Wastewater; Fund:
Wastewater, Account Category: 81 Major Capital,
Quote
During the repair and rehabilitation of the Wastewater Facility heating system, it was
discovered that the two stand-alone units that supply heat to the Cafeteria and the Control
Room are beyond repair. These units, manufactured in 1988, are obsolete and cannot be
replaced in kind. Armand E. Lemire Co., Inc. has determined both rooms can be tied into
the existing steam system easily, with a combined cost of $15,574. As they are the
contractor who has been working on our system to date, we propose the purchase and
installation of these heaters through Lemire,