City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 20, 2018
David L. Boucher, Superintendent
Wastewater Department
Primary Tank Upgrade Project
To approve the contract with Methuen Construction of Plaistow, NH in the amount not to
exceed $3,629,340 for the construction of upgrades to the primary tanks at the
Wastewater Treatment Facility. Funding will be through Department: 169 Wastewater;
Fund: WERF and SRF Loan; Activity: Primary Upgrade Project.
The Nashua Wastewater Treatment Facility is undergoing an upgrade of its primary
tanks. The design was completed at the end of October 2018. Plans and specs were sent
to 6 contractors on October 29, 2018 and the bid opening was held on November 29,
2018. Four bids were received as follows:
Methuen Construction, Inc. 53,629,340
Waterline Industries $4,247,677
TBuck Corporation $4,995,290
Kinsmen Corporation $5,722,000
Methuen Construction bid of $3,629,340 is lower than the engineer’s estimate of $3.7
million. Methuen Construction is well qualified for this project and has performed well in
multiple projects at the wastewater facility in the past.