City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 20, 2018
David L. Boucher, Superintendent
Wastewater Department
Primary Tank Upgrade — Construction Phase Services
To approve the contract with Wright Pierce of Topsham, ME in an amount not to
exceed $375,300 for construction administration services for the Primary Tank
Upgrade Project. Funding will be through: Department: 169- Wastewater; Fund:
SRF Loan; Activity: Primary Tank Upgrade.
Wright Pierce Engineering Contract
The Nashua Wastewater Treatment Facility has been undergoing an upgrade of its
primary tanks, with Wright Pierce as the design engineer, awarded in February of
2017. The project design was completed and the construction went out to bid in
October and 4 bids were received on November 29, 2018. The construction
portion of this project is being recommended for award in Wastewater Motion F,
and construction phase services from Wright Pierce are needed.
Construction is estimated to last 15 months and Wright Pierce’s services include
residential engineering and construction administration. Their cost proposal, at
approximately 10% of the $3,629,340 construction costs, is reasonable at
$375,300.