Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 1/16/2019 - P42

Finance Committee - Agenda - 1/16/2019 - P42

By dnadmin on Mon, 11/07/2022 - 13:13
Document Date
Fri, 01/11/2019 - 11:58
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 01/16/2019 - 00:00
Page Number
42
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__011620…

§ 5.3.2 Adjustments to the Guaranteed Maximum Price on account of changes in the Work subsequent to the
execution of the Guaranteed Maximum Price Amendment may be determined by any of the methods listed in
Section 7.3.3 of AIA Document A201—2007, General Conditions of the Contract for Construction.

§ 5.3.3 In calculating adjustments to subcontracts (except those awarded with the Owner’s prior consent on the basis
of cost plus a fee), the terms “cost” and “fee” as used in Section 7.3.3.3 of ALA Document A201—2007 and the term
“costs” as used in Section 7.3.7 of AIA Document A201—2007 shall have the meanings assigned to them in AIA
Document A201—2007 and shall not be modified by Sections 5.1 and 5.2, Sections 6.1 through 6.7, and Section 6.8
of this Agreement. Adjustments to subcontracts awarded with the Owner’s prior consent on the basis of cost plus a
fee shall be calculated in accordance with the terms of those subcontracts.

§ 5.3.4 In calculating adjustments to the Guaranteed Maximum Price, the terms “cost” and “costs” as used in the
above-referenced provisions of AIA Document A201—2007 shall mean the Cost of the Work as defined in Sections
6.1 to 6.7 of this Agreement and the term “fee” shall mean the Construction Manager’s Fee as defined in Section 3.1
of this Agreement.

§ 5.3.5 If no specific provision is made in Section 5.1.2 for adjustment of the Construction Manager’s Fee in the case
of changes in the Work, or if the extent of such changes is such, in the aggregate, that application of the adjustment
provisions of Section 5.1.2 will cause substantial inequity to the Owner or Construction Manager, the Construction
Manager’s Fee shall be equitably adjusted on the same basis that was used to establish the Fee for the original Work,
and the Guaranteed Maximum Price shall be adjusted accordingly.

ARTICLE 6 COST OF THE WORK FOR CONSTRUCTION PHASE

§ 6.1 Costs to Be Reimbursed

§ 6.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper
performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project
except with prior consent of the Owner. The Cost of the Work shall include only the items set forth in Sections 6.1
through 6.7.

§ 6.1.2 Where any cost is subject to the Owner’s prior approval, the Construction Manager shall obtain this approval
prior to incurring the cost. The parties shall endeavor to identify any such costs prior to executing Guaranteed
Maximum Price Amendment.

§ 6.2 Labor Costs
§ 6.2.1 Wages of construction workers directly employed by the Construction Manager to perform the construction
of the Work at the site or, with the Owner’s prior approval, at off-site workshops.

§ 6.2.2 Wages or salaries of the Construction Manager’s supervisory and administrative personnel when stationed at
the site with the Owner’s prior approval.

(If it is intended that the wages or salaries of certain personnel stationed at the Construction Manager’s principal
or other offices shall be included in the Cost of the Work, identify in Section 11.5, the personnel to be included,
whether for all or only part of their time, and the rates at which their time will be charged to the Work.)

§ 6.2.3 Wages and salaries of the Construction Manager’s supervisory or administrative personnel engaged at
factories, workshops or on the road, in expediting the production or transportation of materials or equipment
required for the Work, but only for that portion of their time required for the Work.

§ 6.2.4 Costs paid or incurred by the Construction Manager for taxes, insurance, contributions, assessments and
benefits required by law or collective bargaining agreements and, for personnel not covered by such agreements,
customary benefits such as sick leave, medical and health benefits, holidays, vacations and pensions, provided such
costs are based on wages and salaries included in the Cost of the Work under Sections 6.2.1 through 6.2.3.

§ 6.2.5 Bonuses, profit sharing, incentive compensation and any other discretionary payments paid to anyone hired
by the Construction Manager or paid to any Subcontractor or vendor, with the Owner’s prior approval.

Page 8 of 16