Exhibit B
Scope of Work
The project scope consists of the design and specification of the lighting and subsequent electrical,
landscape, and civil support for two of the four identified quadrants in the City of Nashua Downtown
Riverfront Master Pian, Final Report, dated August 2017: Quadrant 2: The Greeley House and Cotton
Mill and Quadrant 3: Jackson Falls.
Within these quadrants, scope will include the following areas:
6 Walkway (Quadrant 2 & 3)
® Historic Structures (Quadrant 2)
e Cotton Transfer Bridge (Quadrant 2)
e Floating Water Feature (Quadrant 2)
e Parking Lot (Quadrant 3)
Scope will include providing lighting layouts in CAD in bases provided by City of Nashua, a fixture
schedule and cuts package in PDF format, photometric caiculations for all areas, assistance with
developing and documenting ail integrated lighting, and a provision of estimates of installed cost for
lighting to the cost estimator. The Professional Engineer will be responsible for the circuiting and final
energy code conformance statement. The fixture schedule and notes will be inserted by the Professional
Engineer directly into their contract documents.
PROCESS
This proposal assumes the following process:
SCHEMATIC DESIGN PHASE (DRAFT LIGHTING DESIGN)
@ Review of work to date.
@ Attend initial project kick-off meeting.
e Attend site visit, as required, to see all areas in project scope.
e Develop a Schematic Design Report outlining lighting recommendations for project.
PUBLIC ENGAGEMENT
@ Attend public meeting hosted by the City of Nashua to hear community feedback for Riverfront
lighting design and utilize this feedback to develop preliminary lighting design plan.
PRELIMINARY PLAN
e Prepare preliminary lighting design and electrical package: including fixture cuts (fixtures and
controls), fixture schedule, and scaled lighting layouts.
e Develop 2-3 Photoshop sketch renderings to assist in communicating the lighting design intent.
@ Provide preliminary circuiting intent diagrams and/or control intent narrative.
@ Prepare a preliminary electrical load report, identifying proposed fixtures with associated
wattages, dimming protocols, load types, and voltage requirements.
e Perform in-house verification of lighting design to assure compliance with Energy Code.
® Provide input to cost estimate for lighting and controls (assumed to be by others).
e Prepare photometric studies.
Exhibit A