The H.L. Turner Group Inc.
27 Locke Road Concord. NH 03301 t: 603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
5/11/2022
TASK DESCRIPTION ALLA Herat
PM Structural PE Sr PD Tc HOURS
Segment 11 - 58-60 Main Street Boardwalk
11.1 - Design Bracket Connections 2 16 2 20
11.2 - Transition Design - Boardwalk to Ramp 2 16 2 20
11.3 - Design - Ramp & Piles 2 24 2 28
11.4 - Riverbank Slope E&S 4 16 2 22
11.5 - Final Drawings & Specifications 8 56 4 80 8 156
Se Ae PY GD A ld ee ey ee Ge ee ee ee ee ee ee ee ee ee ee ee ee ee ee ee ee oe
: 112 20 80 16 246
TOTAL HOURS 18 112 20 80 16 246
ESTIMATED ENGINEERING COSTS
Work Estimated
Hours Hourly Rate Costs
Project Manager (PM) 18 S$ 150.00 bs 2,700.00
Structural Engineer (Structural) 112 $ 185.00 $ 20,720.00
Project Engineer (PE) 20 $ 130.00 $ 2,600.00
Sr. Project Designer | (Sr PD) 80 $ 105,00 $ 8,400.00
Technical Coordinator (TC) 16 $ 100.00 $ 1,600.00
246 Total Fully Burdened Labor $ 36,020.00
Subconsultant $ =
Expenses $ 300.00
Estimated Direct Costs $ 300.00
TOTAL ESTIMATED COST= $ 36,3200)