SECTION 02441
CLEANING AND TELEVISION INSPECTION OF PIPELINES
PART 1 - GENERAL
1.01 WORK INCLUDED:
A. The Contractor shall furnish all materials, tools, labor and equipment necessary to clean the
pipeline of debris, and visually inspect by means of a closed-circuit television (CCTV) of
sewers as requested by the Engineer as hereinafter specified.
102 RELATED WORK:
A. Section 01330, SUBMITTALS
B. Section 01331, DOCUMENTATION
103 QUALITY ASSURANCE:
A. The work described herein shall be performed by a company with not less than five (5) years
of experience in providing the required services, employing experienced workers and
experienced supervisory personnel. Supervisory personnel shall have not less than three
years of experience in providing the required services and shall be present at the jobsite
during all work related to the required services.
1.04 SUBMITTALS: IN ACCORDANCE WITH REQUIREMENTS OF GENERAL
SPECIFICATIONS, SUBMIT THE FOLLOWING:
A. Prior to beginning work, submit six (6) sets of the following:
1. Qualifications of the firm/personnel who will perform the work;
2. Description of system proposed for handling existing flows during the various
procedures to be carried out;
3. Description of the system and equipment proposed for cleaning;
4. Description of the system and equipment proposed for root cutting; and
5. Description of the system and equipment proposed for televising the pipe after
cleaning.
2019 Sewer Replacement Project Cleaning and Television Inspection of Pipelines
Nashua, NH 02441-1