Stabilized construction entrance shall conform to the plans and requirements of the
“Erosion and Sediment Control Design Handbook for Developing Areas of New
Hampshire.”
PART 3 —- EXECUTION
3.01 SILTSACKs® AND STABILIZED CONSTRUCTION ENTRANCE:
A. All SILTSACKs® shall be installed in accordance in all catch basins that receive flow
from the disturbed area of the project.with the manufacturer’s recommendations.
B. SILTSACKs® shall not be removed until finish grading, paving and final loam and
seeding have been completed. Maintain SILTSACKs® in good conditions until
removed.
3.06 ROADWAYS AND PAVEMENT AREAS:
A. As soon as possible after utility work has been installed, the roadways shall be brought
to subgrade, and temporary or permanent gravel base and pavement shall be placed.as
per Specifications.
3.07 REMOVAL OF TEMPORARY EROSION CONTROL MEASURES:
A. All temporary erosion control measures shall be removed once the site has been
stabilized with final pavement, and disturbed loam and seed areas have established a
viable stand of grass.
END OF SECTION
2019 Sewer Replacement Project Erosion Control
Nashua, NH 02300-2