not limited to handling of existing wastewater flows, by- pass pumping,
furnishing and installing the necessary coupling, excavation, pipe bedding and
sand blanket, backfill, removal of unsuitable materials and disposal at the City
landfill, furnishing all materials, labor, tools, and equipment necessary to
complete the work complete in place, all as specified in these Specifications
and as directed by the Engineer.
C. 6” PVC CHIMNEY (2 to 6 VF) COMPLETE IN PLACE
Measurement:
The quantity to be measured under ITEM 3 will be the actual number of 6”
PVC Chimneys constructed (2 to 6 vertical feet) by the EACH, complete-in-
place, as specified in these Specifications and as directed by the Engineer.
Payment:
The accepted quantity of 6” PVC Chimneys constructed shall be paid for at the
contract unit price under ITEM 3, and shall be full compensation for the
removal and disposal of the existing chimney, and the construction of the new
chimney, including all pipe, fittings, miscellaneous forming and concrete, and
all labor, tools and any other equipment necessary to complete the work as
specified and as directed by the Engineer.
D. SANITARY WYE COMPLETE IN PLACE
Measurement:
The quantity to be measured under the various subdivisions of ITEM 4 (A and
B) will be the actual number of wyes constructed and measured by the EACH,
complete-in-place, as specified in these Specifications and as directed by the
Engineer.
Payment:
The accepted quantity of wyes constructed shall be paid for at the contract unit
price under the appropriate subdivisions of ITEM 4 (A and B), and shall be full
compensation for furnishing and installing wyes, including all labor, tools and
any other equipment necessary to complete the work as specified and as
directed by the Engineer.
E. NEW OR REPLACE EXISTING SEWER MANHOLE COMPLETE IN PLACE
Measurement:
The quantity of sewer manholes new or replaced under ITEM 5 and will be
measured complete-in-place by the VERTICAL FOOT as measured from the
lowest invert to the top of the manhole casting, complete-in-place, as specified
in these Specifications and as directed by the Engineer.
Payment:
The accepted quantity of sewer manholes new or replaced shall be paid for
at the contract unit price under ITEM 5, and shall constitute full
compensation for removal and disposal of the existing sewer manhole,
constructing new pre-cast sewer manhole, furnishing and installing 30”
2019 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150 - 3