Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P821

Finance Committee - Agenda - 3/6/2019 - P821

By dnadmin on Mon, 11/07/2022 - 13:13
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
821
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

required by a change order.

K. All prices shall include transportation and disposal of excess materials at the City
landfill as applicable.

L. Unit and lump sum prices shall reflect salvage value of all pipe materials and
appurtenances removed as part of the work.

M. All prices shall include costs related to filing and obtaining applicable permits from
local and state agencies.

PART 2 - DESCRIPTION OF PAY ITEMS
2.01 SANITARY SEWER AND DRAIN ITEMS COMPLETE IN PLACE

A. REMOVE AND REPLACE EXISTING SEWER, DRAIN AND SEWER
SERVICE LINES:
Measurement:
The quantity to be measured under the various subdivisions of ITEM 1 (A thru
E) for removal and replacement of existing sewer lines will be measured,
complete-in-place, by the LINEAR FOOT along the completed actual length of
installed pipeline.

Payment:
The accepted quantity of sewer, drain or sewer service pipe installed shall be

paid for at the contract unit price under the appropriate subdivisions of ITEM
1 (A thru E) and shall constitute full compensation for removal and disposal of
the existing sewer pipe and furnishing and installing a new PVC pipe of the
appropriate size, including but not limited to handling of existing wastewater
flows, by- pass pumping, excavation, pipe bedding and sand blanket, backfill,
removal and disposal of unsuitable materials at the City landfill, testing and
video inspections, furnishing all materials, labor, tools, and equipment
necessary to complete the work complete in place, all as specified in these
Specifications and as directed by the Engineer.

B. 10” PVC SDR-35 SEWER STUB 0’ to 9’Depth including Coupling (Charles
Street):
Measurement:
The quantity to be measured under ITEM 2 for installing 10” PVC SDR-35
sewer stub including coupling (Charles Street) will be measured, complete-in-
place, by LUMP SUM.

Payment:
The accepted quantity of sewer stub installed shall be paid for at the contract

unit price under ITEM 2 and shall constitute full compensation for furnishing
and installing a new 10” PVC pipe stub (Approx. 5 LF) from SMH #2 to the
existing 10” sewer stub remaining after removal of SMH S2629, including but

2019 Sewer Replacement Project Measurement and Payment