3. Final acceptance of work shall not be granted until all defective areas are
repaired in accordance with the CIPP manufacturer’s recommendations and to
the Engineer’s satisfaction.
4. Any repairs required by the Engineer as a result of the post construction
internal inspection shall be performed by the Contractor.
5. Contractor shall perform a post construction internal inspection in accordance
with Section 02760. Final acceptance of the work shall not be granted until
post installation inspection has been reviewed and approved by the Engineer.
6. Contractor shall perform testing as specified. Final acceptance of the work
shall not be granted until the appropriately formatted testing results have been
reviewed and approved by the Engineer.
END OF SECTION
2019 CIPP Lining Project CIPP Lining of Existing Sewers (Hot Water or Steam)
Nashua, NH 02650-12