Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P572

Finance Committee - Agenda - 3/6/2019 - P572

By dnadmin on Mon, 11/07/2022 - 13:12
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
572
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

total payment for this item shall be proportional to the percentage of the
contract completed.

2.13 NIGHT WORK

A. ALLOWANCE FOR NIGHT WORK ORDERED BY CITY
Measurement:
Night work, if required and ordered by the City, shall be measured by the
HOUR for work performed by the Contractor’s entire crew between the hours
of 8PM and 7AM. Night hours worked by the Contractor which were not
ordered by the Engineer will not be measured for payment.

Payment:
The contract price for ITEM 10 shall constitute full compensation for the

premium cost of the entire crew including overtime wages, taxes, night
lighting, and any other labor and/or equipment necessary to complete the work
during designated night time hours as specified herein.

Note:
1. Night work may be required in high traffic areas as directed by the Engineer.
An allowance for night work hours has been provided under ITEM 9.

2.14 UNANTICIPATED HAZARDOUS MATERIALS

A. ALLOWANCE FOR UNANTICIPATED HAZARDOUS MATERIALS
Measurement & Payment
ITEM 11 is intended to be a contingency pay item to be used in the event that
unanticipated hazardous material is encountered during the work.
Compensation shall only be paid to the Contractor if unanticipated hazardous
material is encountered and expenditure of the allowance, or portion of the
allowance, is authorized by the Engineer.

An allowance value has been established on the bid form for this item as a
means to include funds in the event that the Contractor is directed to perform
work associated with addressing unanticipated hazardous materials.

Costs for these pay items shall be negotiated between the Engineer and the

Contractor in accordance with provisions for changes in the work in the
General Conditions.

END OF SECTION

2019 CIPP Lining Project Measurement and Payment