Drawings, directions from the Engineer, and as specified herein.
Payment:
The approved quantity of New Vertical Granite Curb shall be paid for at the
contract unit price for ITEM 6H and shall be full compensation for furnishing
and installing new vertical granite curb including crushed gravel base and all
labor, tools and any other equipment necessary to complete the work as
specified in these Specifications and as directed by the Engineer.
2.11 PROJECT START-UP AND PROJECT CLOSE OUT:
A. MOBILIZATION
Measurement:
Mobilization shall be measured as a LUMP SUM as specified herein. The total
cost for this item shall not exceed 5 percent of the total of all bid items
excluding this item.
Payment:
The contract price for ITEM 8 shall constitute full compensation to the
Contractor for the general mobilization and demobilization necessary to make
the contract operational, exclusive of the cost of materials. Payments toward
the lump sum will be made at each payment requisition based on the percent of
contract completed and the balance will be paid at final payment upon
completion of all project requirements. Should the contract be terminated prior
to completion, or the contract work not completed, total payment for this item
shall be proportional to the percentage of the contract completed. No additional
payment will be made if the contract value is increased.
B. WARRANTY INSPECTION:
All warranty inspections and related work shall not be separately measured for
payment but shall be considered incidental to the project.
2.12 MAINTENANCE AND PROTECTION OF TRAFFIC:
A. UNIFORMED POLICE OFFICERS
Measurement:
Uniformed police officers will be measured and paid by the actual number of
hours authorized, as determined by the Engineer. The Contractor shall supply
qualified uniformed officers as stated in Section 618 of the NHDOT Standard
Specifications for Road and Bridge Construction, (Approved and Adopted in
2016). Uniformed officers shall only be used when there are no available
flaggers and the Engineer has previously approved it. Daily coverage needs to
be approved by the Engineer. The Contractor's schedule for utilizing uniformed
officers shall be agreed upon cooperatively with the Engineer.
Payment:
2019 CIPP Lining Project Measurement and Payment
Nashua, NH 01150 - 10