Finance Committee - Agenda - 3/6/2019 - P568

By dnadmin on Mon, 11/07/2022 - 13:12
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
568
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

The approved quantity of hot bituminous pavement shall be paid for at the
contract unit price for ITEM 6B and shall be full compensation for the
furnishing, placing, compacting hot mix asphalt pavement by methods
approved by the Engineer, including all labor, tools and any other equipment
necessary to complete the work as specified in these Specifications and as
directed by the Engineer.

Notes:

1. Temporary and permanent pavement course thicknesses shall
be as specified on the plans, or as ordered by the Engineer.

2. Tack coats shall be applied between all pavement courses and
shall be incidental to this item of work and not measured
separately for payment..

C. SAWED BITUMINOUS PAVEMENT
Measurement:
The quantity to be measured under ITEM 6C, Sawed Bituminous Pavement,
shall be measured by the LINEAR FOOT in accordance with the Contract
Drawings, directions from the Engineer, and as specified herein.

Payment:

The approved quantity of sawed bituminous pavement shall be paid for at the
contract unit price for ITEM 6C and shall be full compensation for saw cutting
bituminous pavement of any depth, including all labor, tools and any other
equipment necessary to complete the work as specified in these Specifications
and as directed by the Engineer.

D. UNCLASSIFIED EXCAVATION
Measurement:
The quantity to be measured under ITEM 6D shall be measured per CUBIC
YARD in place. Measurement for payment of this item shall only apply to the
unclassified excavation for the placement of temporary and permanent
pavement and associated crushed gravel in sewer point repair areas and
manhole frame and cover replacement areas. Quantities shall be measured for
payment as directed and approved by the Engineer. Over-excavated trenches
will not be allowed.

Payment:

The approved quantity of unclassified excavation shall be paid for at the
contract unit price for ITEM 6D and shall be full compensation for the
excavation and disposal of existing pavement and existing unsuitable materials
at the City landfill in order to establish the appropriate subgrade for the
temporary and permanent pavement and associated crushed gravel base
courses, including all labor, tools and equipment necessary to complete the
work as specified in these Specifications and as directed by the Engineer.

2019 CIPP Lining Project Measurement and Payment
Nashua, NH 01150-8

Page Image
Finance Committee - Agenda - 3/6/2019 - P568