M.
required by a change order.
All prices shall include transportation and disposal of excess materials at the City
landfill as applicable.
Unit and lump sum prices shall reflect salvage value of all pipe materials and
appurtenances removed as part of the work.
All prices shall include costs related to filing and obtaining applicable permits from
local and state agencies.
PART 2 - DESCRIPTION OF PAY ITEMS
2.01 SEWER LINING AND VIDEO COMPLETE IN PLACE
A.
B.
CIPP LINING:
Measurement:
The quantity to be measured under the various subdivisions of ITEM 1A for
CIPP lining will be measured, complete-in-place, by the LINEAR FOOT along
the completed CIPP installed from outside edge of beginning sewer manhole to
inside edge of ending sewer manhole (ie. payment is for the actual length of
CIPP pipe installed).
Payment:
The accepted quantity of sewer pipe renovated with cured-in-place-pipe
(CIPP) shall be paid for at the contract unit price under the appropriate
subdivisions of ITEM 1A and shall be full compensation for furnishing and
placing the CIPP liner as specified including furnishing hot water, steam or
ultraviolet light needed to cure the pipe, and all labor, tools and any other
equipment necessary to complete the work. The Contractor is responsible for
any repairs needed to the CIPP should there exist imperfections or defects in
the lining that is judged by the Engineer to cause any problems with sewer
flow such as potential backups or loss in pipe capacity.
PRE-LINING VIDEO:
Measurement:
Pre-lining video for sewer pipe will be measured, complete-in-place, by the
LINEAR FOOT of the actual pipe length videoed.
Payment: .
The accepted quantity of sewer pipe videoed shall be paid for at the contract unit
price under the appropriate subdivisions of ITEM 1A and shall be full compensation
for full cleaning of the sewer line, any and all root cutting, removal and
decanting of debris and disposal at the City landfill, performing pre-lining sewer
pipe video to document the pipe condition and identify all service locations, work
related to developing a report of the pre-lining video, and all labor, tools and any
other equipment necessary to complete the work. The contractor shall provide
2019 CIPP Lining Project Measurement and Payment
Nashua, NH 01150-2