F. Nothing contained herein shall be construed as relieving the Contractor of any of his
responsibilities for protection of persons and property under the terms of the
Contract.
G. Should it be determined by the Engineer that uniformed officers are not required;
flaggers will be provided to maintain traffic flow.
5. Care and Protection of Property
The Contractor shall be responsible for the preservation of all public and private property,
and shall use every precaution necessary to prevent damage thereto. If any direct or
indirect damage is done to public or private property by or on account of any act,
omission, neglect, or misconduct in the execution of the work on the part of the
Contractor, such property shall be promptly restored by the Contractor, at his/her expense,
to a condition similar or equal to that existing before the damage was done, to the
satisfaction of the Engineer.
6. Protection and Relocation of Existing Structures and Utilities
A. All existing buildings, utilities, pipes, poles, wires fences, curbing, property line
markers and other structures must be preserved in place without being temporarily
or permanently relocated, shall be carefully supported and protected from damage
by the contractor. Should such property be damaged, it shall be restored by the
Contractor, at no additional cost to the Owner.
B. The Contractor shall determine the location of all underground structures and utilities
(including existing water services, gas lines, drain lines, electrical lines, and sewers).
Services to buildings shall be maintained, and all costs or charges resulting from
damage thereto shall be paid by Contractor.
C. On paved surfaces the Contractor shall not use or operate tractors, bulldozers, or other
power-operated equipment with treads or wheels which are shaped so as to cut or
otherwise damage such surfaces.
D. All property damaged by the Contractor's operations shall be restored to the
satisfaction of the Engineer to a condition at least equal to that in which it was found
immediately before work was begun. Suitable materials and methods shall be used
for such restoration.
E. Restoration of existing property and structures shall be carried out as promptly as
practicable and shall not be left until the end of the construction period.
7. Maintenance of Flow
A. The Contractor shall at his own cost, provide for the flow of sewers and drains
interrupted during the progress of the work, and shall immediately remove and
dispose of all offensive matter. The entire procedure of maintaining existing flow
shall be fully discussed with the Engineer well in advance of the interruption of any
flow.
2019 CIPP Lining Project Control of Work and Materials