SECTION 01110
CONTROL OF WORK AND MATERIALS
General
Hauling, Handling and Storage of Materials
Open Excavations
Maintenance of Traffic
Care and Protection of Property
Protection and Relocation of Existing Structures and Utilities
Maintenance of Flow
Rejected Materials and Defective Work
Sanitary Regulations
10. Site Investigation
11. Existing Utility Locations — Contractor’s Responsibility
12. Cutting, Fitting and Patching
OPN DARYWN
1. General ‘
Scope: The requirements under this section are applicable to all work completed under
this Contract.
2. Hauling, Handling and Storage of Materials
A. The Contractor shall, at his own expense, handle and haul all materials furnished by
him and shall remove any of his surplus materials at the completion of the work.
B. The Contractor shall provide suitable and adequate storage for equipment and
materials furnished by him that are liable to injury and shall be responsible for any
loss of or damage to any equipment or materials by theft, breakage, or otherwise.
C. All excavated materials and equipment to be incorporated in the Work shall be placed
so as not to injure any part of the Work or existing facilities and so that free access
can be had at all times to all parts of the Work and to all public utility installations in
the vicinity of the work. Materials and equipment shall be kept neatly piled and
compactly stored in such location as will cause a minimum of inconvenience to
public travel and adjoining owners, tenants and occupants.
D. The Contractor shall be responsible for all damages to the work under construction
during its progress and until final completion and acceptance even if progress
payments have been made under the Contract.
3. Open Excavations
A. If/where applicable, all open excavations shall be adequately safeguarded by
providing temporary barricades, caution signs, lights and other means to prevent
accidents to persons, and damage to property. The Contractor shall, at his own
2019 CIPP Lining Project Control of Work and Materials
Nashua, NH 01110-1