W.
Should material enter the system or be deposited during or because of the Contractor’s
activities, this material shall be removed at the Contractor’s expense.
The Contractor may be required to clean structures and pipelines downstream of the
location where material entered the system.
The Contractor may be required to provide television inspection services to verify that
material has been removed.
DISPOSAL OF EXCESS MATERIAL
Excess excavated materials shall be disposed of at the Nashua Landfill. The tipping fee
for clean excess material shall be waived. Contractor shall make arrangements with the
Owner prior to hauling material to the landfill.
Material removed from sewer pipelines and manholes can be delivered and disposed of at
the Nashua Landfill provided the material has been decanted. There will be no fee for
this disposal.
SC -7 of 7