Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P545

Finance Committee - Agenda - 3/6/2019 - P545

By dnadmin on Mon, 11/07/2022 - 13:11
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
545
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

CONTRACTOR’S REPRESENTATIVE

The Contractor shall designate a representative who will be available to respond to
emergency calls by the Owner at any time day and night and on weekends and holidays
should such a situation arise.

Should the City determine action by the City is needed, or if costs are incurred because
the Contractor’s Representative is not available, the City will backcharge the Contractor
for associated expenses.

SCHEDULING AND COORDINATION
Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.

Prior to the start of construction, the Contractor shall submit a comprehensive schedule to
the Engineer for review and acceptance.

The schedule will identify the number of crews and completion dates for all critical
elements of work.

Detailed updates of the schedule shall be submitted to the Engineer for review and
acceptance on at least a monthly interval.

The Engineer may withhold progress payments if acceptable monthly schedule updates
are not submitted.

The Contractor shall not increase the number of crews assigned to the work as identified
in the schedule without providing one week advanced notice to the Engineer.

PROTECTION OF LANDSCAPING

Contractor shall take appropriate measures to protect trees, shrubs and other landscaping.
Branches, limbs and roots shall not be cut except with permission of the Engineer.
Where cutting is necessary, work shall be performed by qualified workers.

REMOVAL OF DEBRIS AND SURPLUS MATERIAL
Neither debris nor surplus material shall be deposited on private property.

Debris and surplus material shall be removed from the project area as promptly as
practical.

If the Contractor should fail to promptly remove debris or surplus material from the

project area, or if Contractor deposits same on private property, progress payment(s) may
be withheld.

PROTECTION OF MANHOLES AND PIPELINES

Appropriate measures will be taken to protect manholes and other structures as well as
pipelines from debris and other materials entering the system through open covers or
grates.