Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P544

Finance Committee - Agenda - 3/6/2019 - P544

By dnadmin on Mon, 11/07/2022 - 13:11
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
544
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

M.

RESTORATION OF EXISTING PROPERTY
Reference is made to Section 01110 Control of Work and Materials Paragraph 7.F of the
Construction Specifications.

Failure to promptly restore existing property and structures including, but not limited to
driveways and lawns, may result in the Engineer’s determination that associated work is
not complete and therefore not eligible for progress payment. Such associated work may
include, but not be limited to paving, pipe installation, catch basins, manholes and
curbing.

ELECTRIC SERVICES

Contractor shall make all necessary applications and arrangements and pay for all fees
and charges for electrical energy for power and light necessary for the proper completion
of this contract during its entire progress. The Contractor shall provide and pay for all
temporary wiring, switches, connections, and meters.

. There shall be sufficient electric lighting so that all work may be done in a safe

and workmanlike manner where there is not sufficient daylight.

WATER FOR CONTRACT WORK
The Contractor shall supply all water needed to complete contract work at no separate
cost to the Owner.

DIMENSIONS OF PHYSICAL FEATURES

Where the dimensions and locations of physical features and structures are of critical
importance in the installation or connections of the work, the Contractor shall verify such
dimensions and locations in the field before fabrication of any material or equipment
which is dependent on the correctness of such information.

SUPERINTENDENCE OF THE WORK
Reference is made to General Conditions Section 6.01, Supervision and Superintendence.

Contractor shall provide appropriate onsite superintendence of all aspects of the work
whether performed by the Contractor or by subcontractors.

Qualified Superintendent(s) shall be assigned for all crews. Contact information will be
provided for all Superintendents.

MAINTENANCE DURING WEATHER EVENTS
The Contractor’s obligation to protect the public traveling through the project site shall
include maintaining safe passage during rain and other weather events.

The Contractor shall plan in advance of forecasted inclement weather events and shall
assign crews to perform maintenance of unpaved areas open to traffic during and after
inclement weather events. Contractor is responsible to coordinate with the Engineer and
other City officials as appropriate.