CHANGES TO THE CONTRACT WORK
At the Owner’s discretion, the Owner may choose to remove portions of the work from
this Contract. The Contractor shall be paid only for work actually performed.
The Owner also reserves the right to add additional work of similar type at other
locations within the City. This may be in place of portions of work removed from the
Contract or may be in addition to the scope of the Contract. Should the value of total
work exceed the contract amount with consideration of additional work to be performed,
the Owner will present a contract amendment proposal to the Contractor.
PARKING REQUIREMENTS
The Contractor is responsible for obtaining the City official “No On-Street Parking” signs
when needed. These signs are available at the City Engineering Office. At the
completion of work, the signs shall be removed and retumed to the City in good
condition.
COOPERATION WITH REFUSE PICKUP
Reference is made to General Conditions Section 17.09, Cooperation with Refuse Pickup.
HAZARDOUS ENVIRONMENTAL CONDITION
Reference is made to General Conditions Section 4. 06, Hazardous Environmental
Condition at Site.
It is not anticipated that hazardous materials will be encountered during excavation for
the contract work.
However, the Contractor should be aware that as yet undiscovered areas with asbestos
containing material or other hazardous contaminants may be encountered.
An allowance (ITEM 10) has been incorporated into the contract to be used if, and only
if, hazardous material is encountered.
Should suspected hazardous material be encountered, the Contractor shall stop work and
immediately notify the Engineer.
Appropriate steps will be taken to cover and protect stockpiles and the work in
accordance with NHDES policies and local, state and Federal requirements.
The Contractor shall cooperate fully with the Engineer as investigations, testing and
referrals are performed.
The allowance shall be used to compensate the Contractor for costs and expenses
incurred as directed by and agreed to be the Engineer.
Negotiations and compensation for work associated with addressing unanticipated
hazardous materials encountered during excavation shall be consistent with provisions in
the Contract for Changes in the Work.