OTHER WORK IN CONTRACT AREA
Other City and utility work may be in progress within the project area during work in this
contract.
It is anticipated that the gas and water companies will be replacing sections of their
existing lines either before or upon completion of the sewer replacement project. The
contractor shall cooperate fully with that work.
The Contractor shall strive to provide coordination with other work within the project
area to minimize disruption.
The Contractor shall notify the Engineer with as much advance notice as reasonably
possible of any concems with other work in the project area.
INTERIM SCHEDULE MILESTONES
In order to facilitate the 2019 Nashua Street Paving Program substantial completion of
work on the following streets shall be completed by the date listed:
West Hollis Street............. June 1, 2019
Lake Street..................000. July 1, 2019
Allds Street...................04 July 1, 2019
WORK HOURS
Reference is made to Section 6.02 Labor; Working Hours of the General Conditions.
Except as stated below, normal working hours shall be from 7:00 AM to 5:00 PM
Monday through Friday. No weekend, holiday or night work will be allowed without
advance written approval of the City Engineer.
The following streets, in addition to the streets listed in General Conditions Section
6.02C, may not be opened or worked in between the hours of 7:00 AM and 9:00 AM and
3:00 PM and 6:00 PM, Monday through Friday of each week:
a. West Hollis Street
b. Allds Street
c. Lake Street
Night work may also be required on the above listed streets, depending on activity,
equipment and time of year.
Requests for work beyond those hours normally allowed on weekdays shall be made by
the Contractor at least 72 hours in advance.
Requests for work on Saturdays, Sundays and holidays shall be made at least one week in
advance.
SC -2 of 7