Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P402

Finance Committee - Agenda - 3/6/2019 - P402

By dnadmin on Mon, 11/07/2022 - 13:11
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
402
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

6. Are flow rates available for bypass flow expectations?

Answer: Specific sanitary and storm water flow rates for the sewers to be lined are
not available; however, a Sewer Infrastructure Map dated 9/27/2018 is
attached to this Addendum for reference. The map shows the Nashua
sewer system as well as general information about dry weather flows at
various CSOs in the City. Please be advised that all sewers to be lined are
combined sanitary/storm sewers subject to wet weather flow.

7. A question was asked regarding the detail of inside drops in sewer manholes?

Answer: Inside drop manholes shall be constructed as detailed on the Standard
Sewer Details — Sheet 35. Inside drops would be used as a pay item if an
existing inside drop was removed for lining of the sewer manhole.
Reconstruction of the drop would be completed as detailed, and the
diameter of the drop shall match the diameter of the incoming pipe.

8. A question was asked regarding the lump sum payment for Mobilization (Item 8)?

Answer: Delete Paragraph 2.03 B of Section 01150, MEASUREMENT AND
PAYMENT, PART 2 - DESCRIPTION OF PAY ITEMS, and substitute
the following:

2.11 PROJECT START-UP AND PROJECT CLOSE OUT:

A. MOBILIZATION
Measurement:
Mobilization shall be measured as a LUMP SUM as specified herein.
The total cost for this item shall not exceed 5 percent of the total of all
bid items excluding this item.

Payment:
The contract price for ITEM 8 shall constitute full compensation to the

Contractor for the general mobilization and demobilization necessary to
make the contract operational, exclusive of the cost of materials.
Payments toward the lump sum will be made at each payment
requisition based on the percent of contract amount completed. Final
payment of this item will be paid based on the percent of the contract
amount completed. Should the contract be terminated prior to
completion, or the contract work not completed, total payment for this
item shall be proportional to the percentage of the contract amount
completed. No additional payment will be made if the contract value is
increased.

- END -