Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P401

Finance Committee - Agenda - 3/6/2019 - P401

By dnadmin on Mon, 11/07/2022 - 13:11
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
401
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

IFB1087-021219
ADDENDUM #2
2019 CIPP Lining Project
Addendum #2 is being issued to respond to final questions received from bidders:
1. Will Davis-Bacon or prevailing wages be in effect for this project?
Answer: Davis-Bacon Act prevailing wage rates do not apply to this project.

2. There is a conflict between the retainage as stated in the Instructions to Bidders,
Article 20 and the Sample Agreement.

Answer: Instructions for Bidders, Article 20, Retainage shall be deleted in its
entirety and replaced as follows:

ARTICLE 20 =RETAINAGE

20.01 Provisions concerning retainage and Contractors’ rights to deposit
securities in lieu of retainage are set forth in the Agreement, Article 6.02
Progress Payments; Retainage.

3. Are we to assume that the Contractor must reinstate catch basins that might be tied
into the pipes to be lined?

Answer: All sewer service connections and catch basin laterals shall be reinstated
after lining.

4. Can you identify the diameter of the existing pipe on Nye Avenue?

Answer: The diameter of the sewer pipe on Nye Avenue is 8-inch.

5. Various questions have been asked regarding the number and location of point repairs?

Answer: Addendum #1 revised the quantity of point repairs and removed the
specific street locations of point repairs. Please be advised that point
repairs may be necessary at various locations as determined by the
Engineer after reviewing the pre-lining or post-lining videos. The
Contractor’s attention is directed to the Supplementary Conditions, Article
A, PROSECUTION OF WORK.

2019 CIPP Lining Project Addendum #2
Nashua, NH Page 1

Page Image