215 ALLOWANCE FOR ADDITIONAL POINT REPAIRS
A. ALLOWANCE FOR ADDITIONAL POINT REPAIRS
Measurement & Payment
Item 12 is an ALLOWANCE value which has been established
in the Bid Schedule as a means to include funds in the event
that the Contractor is directed to perform additional point
repairs in excess of the quantities listed in the Bid Schedule.
Measurement and payment for additional point repairs shall
be based on the unit prices for the appropriate point repair
and roadway restoration items in the Bid Schedule.
5. A concern was raised regarding the maximum rate of $30 per hour for flaggers.
Answer:
The City has decided to bid the cost for flaggers on an hourly basis
without specifying the maximum hourly rate. The Bid Schedule has been
revised to show the quantity of flagger hours under Item 9B. Delete
Paragraph 2.12 B of Section 01150, MEASUREMENT AND PAYMENT,
PART 2 - DESCRIPTION OF PAY ITEMS, and substitute the following:
2.12 MAINTENANCE AND PROTECTION OF TRAFFIC
B. FLAGGERS
Measurement:
The quantity of Flaggers will be measured by the HOUR
based on the actual number of hours authorized, as
determined by the Engineer. The Contractor shall supply
qualified flaggers as stated in Section 618 of the NHDOT
Standard Specifications for Road and Bridge Construction,
(Approved and Adopted in 2016). Daily coverage needs to be
approved by the Engineer. The Contractor's schedule for
flaggers shall be agreed upon cooperatively with the Engineer.
Payment:
The approved quantity of flagger hours shall be paid at the
contract price for ITEM 9B. Payment shall constitute full
compensation to the Contractor for providing qualified
flaggers as required to direct traffic through or around the
Work as ordered by the Engineer, including all labor, high
visibility safety gear, tools and any other equipment necessary
to complete the work as specified herein. Payments to
Contractor will be made based on approved hours and
resulting dollar amounts.
2019 CIPP Lining Project Addendum #1
Nashua, NH
Page 2