To:
From:
Re:
F. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: February 28, 2019
Stephen Dookran, P.E., City Engineer
Engineering Department
2019 CIPP Lining Project
To approve the award of the construction contract for the 2019 CIPP Lining Project to
Kenyon Pipeline Inspection, LLC of Queensbury, New York in the amount of
$2,825,135. Funding will be through: Department: 169 Wastewater; Fund: Bond;
Activity: Sewer Rehab
The 2019 CIPP Lining Project is focused on lining approximately 22,325 linear feet
(4.2 miles) of aging and deteriorating sewer mains. At some locations, preparation of
the sewer main for lining will include point repairs to the pipe and construction of
access manholes. Approximately 23 point repairs will be required and
approximately 10 manholes are estimated to be constructed. Lining of approximately
100 deteriorated manholes is also included in the work.
Seven contractors attended the mandatory pre-bid meeting on January 23. Of these,
four bids were received on February 13" as follows:
Kenyon Pipeline Inspection, LLC $2,825,135.00
Insituform Technologies, LLC $2,977,167.00
Green Mountain Pipeline Services, LLC $3,067,454.50
Granite Inline, LLC $3,087,092.00
The low bid was reviewed and found to be acceptable. It was determined from
checking references that Kenyon Pipe Inspection, LLC has performed satisfactorily
on other sewer projects of this capacity. Work is expected to begin in April.