Technical Specitications FY2019 Paving Program
Contractor shall provide two container types. One shall be of sufficient size and quality to
contain 3 shovels full of asphalt. The other shall be of sufficient size and quality to contain a 6”
diameter core of varying thickness. Containers shall have an area for labeling.
Contractor and City shall agree to order of paving 24 hours prior to placement of mix. Paving
must be completed in a way that does not complicate tonnage tracking for identifying sample
locations. When directed by the Engineer, the Contractor shall pave an entire street or group of
streets before paving other streets.
Cc. MEASUREMENT AND PAYMENT
This item will be paid per Ton of placed, compacted, sampled, and cored hot bituminous
pavement, machine method as approved by the Engineer. A price adjustment for liquid asphalt is
provided in this contract as outlined in Item 900 Liquid Asphalt Adjustment. No payment will be
made for materials delivered but not placed.
Contractor shall record the tons of material placed and compacted for each street. Payment is
contingent upon submittal of quantities and delivery slips in a per street format.
Work and expenses associated with providing loose samples shall be incidental to this item.
Cores shall be measured and paid under Item 1010.9.
