The Contractor shall submit a Traffic Control Plan prior to work on arterial roadways.
This Traffic Control Plan will describe how the Contractor proposes to:
® Stage the work to maintain and control traffic during the lowering of structures
within paved areas; milling operations; and paving operations.
e Maintain access to all residences and businesses through the duration of
construction.
e Lane usage during various phases of work will be described. A minimum of 11-
foot width shall be provided for all lanes open to traffic.
e A minimum of one lane in each direction shall be provided at all times. Should
the Contractor consider it necessary to reduce this requirement to alternating one-
way use, the constraints justifying such a restriction must be explained fully. If
approved at any location in this contract, the use of alternating one-way traffic
will be for a short duration only.
e The Contractor shall describe in the Traffic Control Plan minimum conditions
which will be provided at the end of working hours. At a minimum, if a vertical
break of more than one inch exists along the direction of travel and vehicles are
operating on the higher surface, a pavement fillet will be provided along the
break. The pavement fillet shall be constructed with a slope of 12 inches
horizontal for each one inch vertical.
e Full lane use shall be maintained for weekend and holiday periods.
REMOVAL OF DEBRIS AND SURPLUS MATERIAL
Neither debris nor surplus material shall be deposited on private property.
Debris and surplus material shall be removed from the project area as promptly as
practical.
If the Contractor should fail to promptly remove debris or surplus material from the
project area, or if Contractor deposits same on private property, progress payment(s) may
be withheld.
DISPOSAL OF SURPLUS EXCAVATED MATERIAL
All milled (cold planed) pavement shall be delivered to the Four Hills Landfill in Nashua,
NH. Unless otherwise specified herein, all other excess material not required for use on
the project shall be disposed of legally and safely by the Contractor at his discretion
outside of and away from the limits of the project, without additional compensation.
MAINTENANCE DURING WEATHER EVENTS
The Contractor’s obligation to protect the public traveling through the project site shall
include maintaining the work and maintaining safe passage during rain and other weather
events.
The Contractor shall plan in advance of forecasted inclement weather events and shall
assign crews to perform maintenance of unpaved areas open to traffic during and after
inclement weather events. Contractor is responsible to coordinate with the Engineer and
other City officials as appropriate.