Technical Specifications FY2019 Paving Program
ITEM 618.7 - FLAGGERS
A. SCOPE
This work shall consist of furnishing qualified flaggers, as required to direct traffic through or
around the Work as ordered by the Engineer.
B. MATERIALS AND CONSTRUCTION
The Contractor shall supply qualified flaggers as per the latest approved NHDOT Standard
Specifications for Road and Bridge Construction. Daily coverage needs to be approved by the
Engineer.
OF MEASUREMENT AND PAYMENT
Flaggers will be measured by the actual number of hours authorized, as determined by the
Engineer. This item has a budgeted allowance as shown on the Bid Form. In no case shall the
gross hourly rate exceed $30/hour for straight time work, and $45/hour for overtime work.
Payments to Contractor will be made based on approved hours and resulting dollar amounts.
Contractor shall record the number of hours for each flagger used. Hours shall be recorded on a
per street basis. Payment is contingent upon submittal of quantities in a per street format.
Payment will not be made for flaggers who are not equipped with appropriate equipment or who
do not follow standard practice in performing their duties.