Technical Specifications FY2019 Paving Program
ITEM 609.01 - GRANITE CURBING
A. SCOPE
This work shall consist of constructing curb as shown on the plans or as ordered by the Engineer.
Work includes furnishing, placing, and cleanup work associated with the installation of the curb.
Curb shall be installed on a properly graded, compacted bed of crushed gravel subgrade.
B. MATERIALS AND CONSTRUCTION
The Contractor shall furnish all materials, labor and equipment necessary for setting of granite
curb in accordance with relevant provisions of Section 609 of the NHDOT Standard
Specifications for Road and Bridge Construction, latest edition, and City of Nashua Standard
Specifications for Sidewalk Construction, latest edition. The most stringent specifications shall
apply unless otherwise directed by the Engineer.
C. MEASUREMENT AND PAYMENT
Granite curb will be measured by the linear foot to the nearest 0.1 foot, from end to end along the
lower edge of the exposed face of the curbing and shall include all required excavation and base
course material.
Payment for constructing granite curb shall be at the contract unit price per linear foot, complete
in place, and shall include full compensation for material, labor, equipment, and all else needed
to complete the work under this item.