Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/6/2019 - P150

Finance Committee - Agenda - 3/6/2019 - P150

By dnadmin on Mon, 11/07/2022 - 13:10
Document Date
Fri, 03/01/2019 - 12:37
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/06/2019 - 00:00
Page Number
150
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__030620…

15.

16.

17.

18.

If the Contractor should fail to promptly remove debris or surplus material from the

project area, or if Contractor deposits same on private property, progress payment(s) may
be withheld.

DISPOSAL OF SURPLUS EXCAVATED MATERIAL

All milled (cold planed) pavement shall be delivered to the Four Hills Landfill in Nashua,
NH. Unless otherwise specified herein, all other excess material not required for use on
the project shall be disposed of legally and safely by the Contractor at his discretion
outside of and away from the limits of the project, without additional compensation.

MAINTENANCE DURING WEATHER EVENTS

The Contractor’s obligation to protect the public traveling through the project site shall
include maintaining the work and maintaining safe passage during rain and other weather
events.

The Contractor shall plan in advance of forecasted inclement weather events and shall
assign crews to perform maintenance of unpaved areas open to traffic during and after
inclement weather events. Contractor is responsible to coordinate with the Engineer and
other City officials as appropriate.

Contractor shall be prepared to respond in a timely manner if the City determines that
circumstances warrant action when the Contractor is not onsite.

DRAINAGE
The Contractor shall provide necessary measures to provide drainage and minimize
ponding on paved and unpaved surfaces.

The Contractor shall be responsible to provide means for stormwater runoff to enter the
drainage system at locations where structures are lowered in advance of milling or
reclamation.

During the preconstruction meeting, the Contractor shall describe provisions to be made
for drainage. Provisions made and methods used shall have been proven by successful
use on past projects of a similar nature.

PROTECTION OF MANHOLES, CATCH BASINS AND PIPELINES

Appropriate measures will be taken to protect manholes, catch basins and other structures
as well as pipelines from debris and other materials entering the system through open or
removed covers or grates.

Should material enter the system during the Contractor’s activities, this material shall be
removed in a timely manner at the Contractor’s expense.

The Contractor may be required to clean structures and pipelines downstream of the
location(s) where material entered the system.

The Contractor may be required to provide television inspection services to verify that
material has been removed.