INTERIM MILESTONES FOR SUBSTANTIAL COMPLETION
The following Substantial Completion Milestones shall be met:
50 percent of the total length of all roadway segments in the contract shall be
substantially complete by July 17, 2019.
85 percent of the total length of all roadway segments in the contract shall be
substantially complete by September 6, 2019.
The entire length of all roadway segments shall be substantially complete by October 15,
2019.
WORK HOURS
Reference is made to Section 6.02 Labor; Working Hours of the General Conditions.
Except as stated below, normal working hours shall be from 7:00 AM to 5:00 PM
Monday through Friday. No weekend, holiday or night work will be allowed without
advance written approval of the City Engineer.
The following streets, in addition to the streets listed in General Conditions Section
6.02C, may not be opened or worked in between the hours of 7:00 AM and 9:00 AM and
3:00 PM and 6:00 PM, Monday through Friday of each week:
a. West Hollis Street
b. Allds Street
c. Lake Street
Requests for work beyond those hours normally allowed on weekdays shall be made by
the Contractor at least 72 hours in advance.
Requests for work on Saturdays, Sundays and holidays shall be made at least one week in
advance.
Contractor should not assume requests for hours beyond the hours and days normally
allowed will be approved. Requests will be considered on a case by case basis.
CONTRACTOR’S REPRESENTATIVE
The Contractor shall designate a representative who will be available to respond to
emergency calls by the Owner at any time day and night and on weekends and holidays
should such a situation arise.
Should the City determine action by the City is needed or other costs are incurred
because the Contractor’s Representative is not available, the City will backcharge the
Contractor for associated expenses.
SCHEDULING AND COORDINATION
Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.