During the progress of the Work CONTRACTOR shall keep the Site and other areas free from accumulations of
waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Cleaning:
Prior to Substantial Completion of the Work CONTRACTOR shall clean the Site and make it ready for utilization
by OWNER. At the completion of the Work CONTRACTOR shall remove from the Site all tools, appliances,
construction equipment and machinery, and surplus materials and shall restore to original condition all property not
designated for alteration by the Contract Documents.
D. Loading Structures:
CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will endanger
the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures
that will endanger it.
E. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless
OWNER, ENGINEER, ENGINEER’s Consultant, and the officers, directors, partners, employees, agents, and other
consultants of each and any of them from and against all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration
or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable, brought by any
such OWNER or occupant against OWNER, ENGINEER, or any other party indemnified hereunder to the extent
caused by or based upon CONTRACTOR’ performance of the Work.
6.12 Record Documents
A. CONTRACTOR shall maintain in a safe place at the Site one record copy of all Drawings, Specifications, Addenda,
Written Amendments, Change Orders,
Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during
construction. These record documents together with all approved Samples and a counterpart of all approved Shop
Drawings will be available to ENGINEER for reference. Upon completion of the Work, these record documents,
Samples, and Shop Drawings will be delivered to ENGINEER for OWNER.
B CONTRACTOR shall mark up one set of paper prints to show the As-built conditions. They shall include all the
information shown on the Contract Drawings and a record of all deviations, modifications, or changes from those
Drawings, however minor, which were incorporated in the Work, all additional work not appearing on the Contract
Drawings and all changes which are made after final inspection of the Contract Work. These As-built marked prints
shall be kept current and available on the job site at all times. All changes from the Contract Drawings which are made
in the Work or additional information which might be uncovered in the course of construction shall be accurately and
neatly recorded as they occur by means of details and notes. No construction work shall be concealed until it has been
inspected, approved, and recorded. The As-built marked prints will be jointly inspected for accuracy and completeness
by the ENGINEER'S representative and a responsible representative of the CONTRACTOR prior to submission of the
monthly pay estimate. Failure to keep the As-built marked prints on a current basis shall be sufficient justification to
suspend pay estimates. The drawings shall show the following information, but not be limited to:
1. The location of any utility lines or other installations of any kind or description known to exist within the
construction area. The location includes dimensions of permanent features.
2. The location and identification of all surface installations within 100 feet of the construction work.
3. The location and dimensions of any changes within the building or structure.