b. A description of the portion of the work or improvement which each subcontractor named in the bid
will complete.
2. The CONTRACTOR shall list in his bid the name of a subcontractor for each portion of the project that
will be completed by a subcontractor.
3. A CONTRACTOR whose bid is accepted shall not substitute any person for a subcontractor who is
named in the bid, unless:
a. The awarding authority objects to the subcontractor, requests in writing a change in the
subcontractor and pays any increase in costs resulting from the change; or
b. The substitution is approved by the awarding authority and:
(i) The subcontractor, after having a reasonable opportunity, fails or refuses to execute a written
contract with the CONTRACTOR which was offered to the subcontractor with the same terms that
all other subcontractors on the project were offered;
(ii) The named subcontractor files for bankruptcy or becomes insolvent; or
(iii) The named subcontractor fails or refuses to perform his subcontract within a reasonable time
or is unable to furnish a performance bond and payment bond.
I. If blasting or use of explosives is necessary for prosecution of Work, the CONTRACTOR shall provide the
ENGINEER with a blasting plan in compliance with OSHA, State, and local regulations, laws, ordinances, and
requirements. CONTRACTOR shall exercise the utmost care not to endanger life or property. CONTRACTOR shall
be responsible for all damage resulting from the use of explosives. CONTRACTOR shall notify each property
OWNER and utility company having structures or facilities in proximity to the site of the work of its intentions to use
explosives. Such notice shall be given sufficiently in advance to enable the utility companies to take such steps as they
may deem necessary to protect their property from injury.
6.10 Taxes
A. CONTRACTOR shall pay all sales, consumer, use, and other similar taxes required to be paid by CONTRACTOR
in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance
of the Work
6.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas
1. CONTRACTOR shall confine construction equipment, the storage of materials and equipment, and the
operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably
encumber the Site and other areas with construction equipment or other materials or equipment. CONTRACTOR
shall assume full responsibility for any damage to any such land or area, or to the OWNER or occupant thereof, or
of any adjacent land or areas resulting from the performance of the Work.
2. Should any claim be made by any such OWNER or occupant because of the performance of the Work,
CONTRACTOR shall promptly settle with such other party by negotiation or otherwise resolve the claim by
arbitration or other dispute resolution proceeding or at law.
B. Removal of Debris During performance of the Work: