make no changes or relocations without the prior written approval of OWNER. CONTRACTOR shall report to
ENGINEER whenever any reference point or property monument is lost or destroyed or requires relocation because of
necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such
reference points or property monuments by professionally qualified personnel.
4.06 Hazardous Environmental Condition at Site
A. Reports and Drawings: Reference is made to the Supplementary Conditions for the identification of those reports
and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that have been utilized by
the ENGINEER in the preparation of the Contract Documents.
B. Limited Reliance by CONTRACTOR on Technical Data Authorized: |. CONTRACTOR may rely upon the general
accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract
Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such
“technical data,” CONTRACTOR may not rely upon or make any Claim against OWNER, ENGINEER or any of
ENGINEER’s Consultants with respect to:
1. The completeness of such reports and drawings for CONTRACTOR’s purposes, including, but not limited to,
any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by
CONTRACTOR and safety precautions and programs incident thereto; or
2. Other data, interpretations, opinions and information contained in such reports or shown or indicated in such
drawings; or
3. Any CONTRACTOR interpretation of or conclusion drawn from any “technical data” or any such other data,
interpretations, opinions or information.
C. CONTRACTOR shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the
Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be
within the scope of the Work. CONTRACTOR shall be responsible for a Hazardous Environmental Condition created
with any materials brought to the Site by CONTRACTOR, Subcontractors, Suppliers, or anyone else for whom
CONTRACTOR is responsible.
D. If CONTRACTOR encounters a Hazardous Environmental Condition or if CONTRACTOR or anyone for whom
CONTRACTOR is responsible creates a Hazardous Environmental Condition, CONTRACTOR shall immediately: (i)
secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected
thereby (except in an emergency as required by paragraph 6.16); and (iii) notify OWNER and ENGINEER (and
promptly thereafter confirm such notice in writing). OWNER shall promptly consult with ENGINEER concerning the
necessity for OWNER to retain a qualified expert to evaluate such condition or take corrective action, if any.
E. CONTRACTOR shall not be required to resume Work in connection with such condition or in any affected area
until after OWNER has obtained any required permits related thereto and delivered to CONTRACTOR written notice:
(i) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work; or (ii)
specifying any special conditions under which such Work may be resumed safely. If OWNER and CONTRACTOR
cannot agree as to entitlement to or on the amount or extent, if any, of any adjustment in Contract Price or Contract
Times, or both, as a result of such Work stoppage or such special conditions under which Work is agreed to be
resumed by CONTRACTOR, either party may make a Claim therefore as provided in paragraph 10.05.
F, If after receipt of such written a notice CONTRACTOR does not agree to resume such Work based on a reasonable
belief it is unsafe, or does not agree to resume such Work under such special conditions, then OWNER may order the
portion of the Work that is in the area affected by such condition to be deleted from the Work. If OWNER and
CONTRACTOR cannot agree as to entitlement to or on the amount or extent, if any, of an adjustment in Contract Price
or Contract Times as a result of deleting such portion of the Work, then either party may make a Claim therefore as
GC - 15 of 53