SECTION 02950
CLEANUP AND SITE RESTORATION
PART 1 - GENERAL
1.1
SCOPE OF WORK
A.
Furnish all labor, materials, equipment and incidentals necessary to complete
the work under this Section including operations which cannot be specified in
detail as separate items, but can be sufficiently described as to the kind and
extent of Work involved.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
3.1
3.2
CLEANUP
A.
During the course of the work, CONTRACTOR shall keep the site of his
operations in as clean and neat a condition as is possible. Lumber, equipment,
temporary structures, and other refuse remaining from the construction
operations shall be removed from the site. CONTRACTOR shall leave the entire
site in a neat and orderly condition.
B. It shall be CONTRACTOR's responsibility to dispose of all excess material and
residue resulting from construction operations. Excess materials consisting of
soil, rock or boulders shall be disposed of by CONTRACTOR in on-site areas
designated by OWNER.
C. Upon establishment of vegetation, CONTRACTOR shall remove all silt
fence/erosion control structures under the direction of OWNER.
INCIDENTAL WORK
A. CONTRACTOR shall do all incidental Work not otherwise specified but
obviously necessary for the proper completion of the Contract in accordance
with the Drawings and Specifications.
{END OF SECTION 02950]
P:\3000s\3066.09\Source Files\Type II App\Specifications\Division 2 Specifications\02950 Cleanup and Site Restoration.docx
File No. 3066.09 Cleanup and Site Restoration 02950 - 1 of 1 December 2017