ENGINEER or OWNER will observe work for provisional acceptance at the end
of the eight (8) week grass maintenance period, and upon the written request
of CONTRACTOR, which must be received at least ten (10) days before the
anticipated date of observation.
A satisfactory stand will be defined as a section of grass of 10,000 square feet
or larger that has:
1. No bare spots larger than three square feet.
2. No more than ten percent of total area with bare spots larger than one
square foot.
3. No more than fifteen percent of total area with bare spots larger than 6
inches square.
4, The observations by ENGINEER or OWNER will determine whether
maintenance shall continue in any area or manner.
After all necessary corrective work and cleanup has been completed,
ENGINEER or OWNER will acknowledge the provisional acceptance of the
seeded areas. CONTRACTOR's responsibility for maintenance of seeded areas,
or parts of seeded areas shall cease on receipt of provisional acceptance.
3.4 | GUARANTEE PERIOD AND FINAL ACCEPTANCE
A.
All seeded areas shall be guaranteed by CONTRACTOR for not less than one full
year from the time of provisional acceptance.
At the end of the guarantee period, ENGINEER or OWNER will make
observations upon written request submitted by the CONTRACTOR at least ten
days before the anticipated date. Seeded areas not demonstrating satisfactory
stands as outlined above, as determined by ENGINEER or OWNER, shall be
renovated, reseeded, and maintained meeting all requirements as specified
herein.
After all necessary corrective work has been completed, ENGINEER or OWNER
shall acknowledge in writing the final acceptance of the seeded areas.
[END OF SECTION 02830]