Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/20/2019 - P211

Finance Committee - Agenda - 3/20/2019 - P211

By dnadmin on Mon, 11/07/2022 - 13:08
Document Date
Wed, 03/20/2019 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/20/2019 - 00:00
Page Number
211
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__032020…

January 10, 2019 Page 5
20190110 Bid Item Defintions.docx 3066.09

delivery, unloading, moving, and storage of the geomembrane, as well as the amount of
geomembrane used for overlap and in anchor trenches.

Payment will be made on a per square yard basis for the Secondary Geomembrane
installed within the limit of waste containment as measured by survey of the actual plan
area. Geomembrane installed beyond the limit of waste containment is incidental to this
Bid Item.

c. Secondary Drainage Geocomposite includes all labor, materials, equipment, tools, and
apparatus needed to furnish and install the Secondary Drainage Geocomposite within the
Phase III limit of waste containment as shown on the Drawings and in accordance with
the Specifications. The unit price for this Bid Item includes all pre-approval and quality
contro] testing, delivery, unloading, moving, and storage of the Drainage Geocomposite,
as well as the amount of Secondary Drainage Geocomposite used for overlap and in
anchor trenches.

Payment will be made on a per square yard basis for the Secondary Drainage
Geocomposite installed within the limit of waste containment as measured by survey of
the actual plan area. Secondary Drainage Geocomposite installed beyond the limit of
waste containment is incidental to this Bid Item.

d. Secondary Drainage Sand includes all labor, materials, equipment, tools, and apparatus
needed to furnish and place a 12-inch thick lift of Drainage Sand over the Secondary
Drainage Geocomposite in the Phase III base area as indicated on the Drawings, in
accordance with the Specifications.

Payment for this Bid Item will be made on a cubic yard basis of in-place secondary
Drainage Sand in the Phase III base area as measured by survey of the actual plan area.

e. Geosynthetic Clay Liner (GCL) includes all labor, materials, equipment, tools, and
apparatus needed to furnish and install the GCL within the Phase III limit of waste
containment as shown on the Drawings and in accordance with the Specifications. The
unit price for this Bid Item includes all pre-approval and quality control testing, delivery,
unloading, moving, and storage of the GCL, as well as the amount of GCL used for overlap
and in anchor trenches.

Payment will be made on a per square yard basis for the GCL installed within the Phase
III limit of waste containment as measured by survey of the actual plan area. GCL
installed beyond the limit of waste containment is incidental to this Bid Item.

f. Primary 60-mil Thick Textured HDPE Geomembrane includes all labor, materials,
equipment, tools, and apparatus needed to furnish and install the Primary 60-mil Thick
Textured HDPE Geomembrane within the Phase III limit of waste containment as shown
on the Drawings and in accordance with the Specifications. The unit price for this Bid
Item includes all pre-approval and quality control testing, delivery, unloading, moving,
and storage of the geomembrane, as well as the amount of geomembrane used for
overlap and in anchor trenches.